Slideshow image

Lift Update - The construction of the lift shaft is complete and electrical wiring is roughed in. 

  • Framing of the shaft is complete
  • The outside entrance has been created by removing a portion of the foundation wall.
  • Electrical rough-in work is complete.
  • Control wiring rough-in work is complete.
  • Waiting on electric inspection, framing inspection, and subsequent drywall installation.
  • The project is on budget.

It is important to keep everyone (especially children) from the area of that opening. Please respect caution tape/signage, and all barriers. 

Lift installation has been delayed due to shipping delays by the manufacturer.  Best guess is installation completion by mid-February.

We are very excited that soon all parishioners and visitors to CLC will be able to join us worship and fellowship with convenient access to all levels of the building.